REVIEW OF PHYSICAL PROGRESS
 
Types of Activities Cumulative Progress Upto Dec., 2005 (EOP)
Project Target Actual Upto Dec. 2005 Percentage (%)
RTAPP TPR /PIC RTAPP TPR /PIC
1) Social Mobilization Component
No. of VGMs Selected and Trained 5850 7091 6760 116% 95%
No. of Groups formed 1170 1495 1508 129% 101%

No. of Centres formed

277 292 297 107% 102%
No. of Empowered Centres formed 223 219 161 72% 74%
No. of Male VGMs 3510 3194 3197 91% 101%

No. of Female VGMs
2340 3897 3563 152% 91%
Male-Female Ratio 60:40 45:55 - 47:53  
2) Procurement and Distribution of Total Livestock Packages
Total No. of Packages procured and distributed 7901 7901 8218 108% 104%
3) Types and nos. of Packages Distributed
Milk Cows 3170 3619 3785 119% 105%

Heifers
1981 514 464 23% 90%
Total of Milch Cows 5151 4133 4249 82% 103%
Fattening Cattle 1981 1866 1776 90% 95%
Total Cattle 7132 5999 6025 84% 100%
Types and nos. of Packages Distributed
Goat Packages 156 515 634 406% 123%
Pig Packages 16 120 137 856% 114%
Poultry Packages 119 90 61 51% 68%
Duck Packages 80 516 683 854% 132%
Crop/Fodder Packages 161 665 706 438% 106%
Bio-digesters 237 305 283 119% 93%
Others 00 08 06 - 75%
Total Packages 7901 8218 8535 108% 104%
4) Physical Progress of Infra-structures
  4.1 Community Dairy Enterprises(CDE)/ Milk Cooling Plants
    10 Milk Cooling Plants have been installed into seven CDEs. 100% completed
  4.2 Milk Processing (Milk-Pro) Plants
    04 Milk Pro Pasteurising machines were installed 100% completed
  4.3 Community Feed Mills (CFM)
    03 CFM were set up as against 02 in Prodoc one each under every farm. 150% completed
   
 
Trademarks & Copyright © 1998 Grameen Communications | All Rights Reserved.